Havre des Pas Resurfacing work has resumed.
It was suspended last week because technical issues at the Ronez manufacturing plant meant asphalt couldn't be supplied.
Work that didn't need asphalt has continued since.
A government spokesperson says, as things stand, the project should finish before the end of this month as scheduled.
The work started on 10 January.

Concerns were raised in the last States sitting about the disruption this work was causing.
Infrastructure Minister Deputy Kevin Lewis said the work was planned in the early months of the year as traffic figures demonstrated that it was the quietest period for the road network and have the least impact on the bus network.


JET to receive £2.5 million for 2027
Jersey has 'strong' supply lines and 'sufficient fuel supplies' despite Iran war
Applications open for recreational Bluefin Tuna fishing permits
Occupation survivors write a book to keep Liberation Day alive
Jersey's government spent £1.18 billion in 2025
JSPCA to close Sion charity shop
Jèrriais film set to hit the screens at 13th Parish Film Festival
Muratti Tickets on now on sale