The long-awaited skate park at Les Quennevais is expected to open this Saturday (4 February)
The highly-anticipated unveiling seems to have been confirmed on Facebook by the Jersey Skateparks Association.
Spades were officially in the ground on 3 February 2022, following years of campaigning for a skate facility.
Skaters celebrated the beginning of work on the site in February 2022.
The £1.8 million park has been plagued by delays, with work initially hoped to have finished by May last year.
That was pushed back to July - in time for the school summer holidays, and then to mid-October 2022.
Sports Minister, Deputy Lucy Stephenson then said that the park was due to open in mid-December, but it didn't. The new date of January 2023 was given.
The delays where put down to logistical issues of getting supplies into the island. Deputy Stephenson told Channel 103 in November that Jersey is 'not immune' to global supply issues, made worse by the war in Ukraine.
The park will open at 2pm on Saturday 4 February, with a small opening ceremony happening at 1.30pm.

Ombudsman issues advice about mis-sold car loans
'Music Muratti' for young musicians in the Channel Islands
Jersey celebrates 81 years of Liberation
Victoria College twins with secondary school in Bad Wurzach
Jet2 increases capacity to Jersey by 140% for summer 2027
10-day Liberation International Music Festival gets underway
Flower mural in St Brelade's dubbed 'graffiti' and covered up
Future politicians called to action over visitor economy at 'tipping point'